: :inin Kyiv (EET)

Key Tender for Units 5, 6 of Bulgaria’s Kozloduy NPP at Standstill


Units 5 and 6 of Bulgaria’s Kozloduy nuclear power plant need a replacement of the automated neutron flux control system in order to have their capacity increased.
The measure is part of the life extension and modernization program for units 5 and 6 of the Kozloduy NPP, according to investor.bg.
The replacement of the system was requested by the chief constructor, OKB Hydropress, in order to allow the increase of the capacity of the two N-plant units and the granting of a life-extension.
The managing body of the Kozloduy NPP launched a tender procedure for the selection of a supplier of the technology …read more